Ather Energy has deferred the rollout of its entry-level Konarc model to the fourth quarter of fiscal year 2027, moving it back from the first-quarter schedule originally revealed when the scooter debuted. Chief Executive Officer Tarun Mehta explained during an analyst conference that introducing the baseline version while manufacturing capabilities remain constrained would siphon away volume from more profitable, higher-margin offerings. The Konarc is instead being introduced gradually, kicking off in Rajasthan and Uttar Pradesh before expanding to additional central, northern, and western territories, with southern regions scheduled to receive the model once output allows.

Production Bottlenecks and Surging Demand

The electric vehicle manufacturer is currently grappling with strong order backlogs that outpace its manufacturing output, leading to approximately 18,000 to 20,000 units of monthly retail demand remaining unfulfilled. During the July to September period of fiscal year 2027, customer pre-orders surged by more than two times compared to the same timeframe a year prior, reaching approximately 1.80 lakh units. Meanwhile, average monthly manufacturing hovered around 33,000 units, pushing the primary Hosur manufacturing facility to operate at up to 98 percent of its maximum capacity during Q2 FY2027.

Ather Konarc studio image
Ather Konarc studio image

CEO Tarun Mehta noted on the investor call that the company is missing out on roughly 20,000 units every month in untapped retail potential due to these supply limitations. To alleviate the bottleneck, Ather's board has sanctioned a capital expenditure of Rs 122 crore to expand overall yearly output by 2.25 lakh units across its manufacturing footprints in Hosur and AURIC.

Capital Allocation and Plant Expansion Details

  • Hosur Facility: Allocates up to Rs 58 crore to elevate yearly output from 4.2 lakh units to 4.95 lakh units by the month of December, alongside a new battery line scheduled for Q3 FY2028.
  • AURIC Facility: Directs Rs 64 crore toward the Chhatrapati Sambhajinagar plant, which initiates phased commercial operations in December featuring a starting annual capacity of 5 lakh units.
  • Combined Footprint: Increases total annual nameplate capacity to approximately 11.45 lakh units, up from the current 9.2 lakh units.

Market Impact and Future Outlook

For prospective buyers and retail partners, the capacity enhancements signify that Ather Energy is actively working to resolve delivery delays and address the massive backlog of 1.80 lakh pre-orders. By scaling up the Hosur site and bringing the AURIC plant online by December, the manufacturer aims to close the gap between its strong market demand and factory throughput, paving the way for the eventual wide-scale availability of the entry-level Konarc variant in later quarters.